PROJECT 1 - Electrical
Upgrade
| Client: |
UnitedGroup |
| Project: |
33KV Electrical Cable Upgrade at Berrima Cement Plant |
| Start Date: |
08/05/2006 |
| Completion Date: |
12/05/2006 |
Scope of Works
Drill 205m and install 2 x 125mm Continuous Electrical
Conduit Between the Railway Line and the existing table Drain inside the Berrima Cement
Plant without disruption to the plants day to day operations.
Project Sensitivity
Existence of 11kv Electricity Cables, Large Table
Drain, Railway Line. All construction was not to impact on the Cement Plants day to day
operations. Work to strict OH&S Cement Plant guidelines at all times.
|