PROJECT 4 - Minchinbury Telecommunications
Upgrade
| Client: |
NDGC (TELSTRA) |
| Project: |
2.4km Build for Telecommunications Upgrade in Minchinbury |
| Start Date: |
02/01/2006 |
| Completion Date: |
23/01/2006 |
Scope of Works
Install 1.3Km of new 100mm Telecommunications Conduit
from Roper Rd to Sargents Rd including the crossing of Ropes Creek at 4.6m in depth,
Install 6 new Telecommunications Pits, Haul 2.4Km 12 SMOF through existing build and new
build from Roper Rd and terminate fibre into customer Premises in Sargents Rd in
Minchinbury.
Project Duration
16 working days from start to completion
Project Sensitivity
Aboriginal Land near Ropes Creek, Existing Major
Energy Australia Cables, Large Water Main in vicinity, RTA owned Assets Roper Rd and
Carlisle Ave. Maintain minimal disruption to residence and the surrounding environment.
Project Completion Photos that show little or no
evidence of construction work after completion of Project.
Project Completion Photos
These show little or no evidence of construction work after completion of Project.
Bastow Civil Constructions Pty Ltd take pride in ensuring the environment is fully
restored to its original condition after the completion of the project from the photos
above you can see that we take care to reinstate the ground conditions to ensure that
there is little if no evidence that our company has been conducting civil construction.
|