PROJECT 5 - Riverstone Electrical Upgrade
| Client: |
Integral Energy |
| Project: |
195m Build for Electrical Upgrade in Riverstone |
| Start Date: |
13/06/2006 |
| Completion Date: |
19/06/2006 |
Scope of Works
Install 195m of 4 x 125mm conduit and 2 x 50mm conduit along Riverstone Parade in Riverstone by trenching method of installation.
Project Duration
5 working days from start to completion.
Project Sensitivity
Rural area during winter, foggy and windy conditions for the duration of the project.
Ground Conditions all ROCK.